Water Networks Cost Indices by Major and Sub Groups in the West Bank for the Years 2019 and 2018

(Base Month January 2010=100)

 

Click Here To Download Excel File

Major and Sub Groups 

West Bank

Average 2018

Average 2019

% Change

Water Reservoirs

109.78

106.69

-2.82

Excavations

125.50

123.84

-1.33

Concrete

104.39

103.47

-0.89

Iron

109.59

101.05

-7.79

Construction work and paint

121.19

123.30

1.74

Miscellaneous

107.40

106.87

-0.49

Administrative expenses

118.57

119.42

0.71

Water Networks

115.78

116.66

0.76

Excavations

125.50

123.84

-1.33

Deface Materials

102.68

102.55

-0.12

Asphalt, bitumen mixture and  its products

87.05

87.41

0.41

Plastic and steel Pipes 

121.13

123.00

1.54

Administrative expenses

118.57

119.42

0.71

Wages and other costs

132.22

133.13

0.68

General  index

113.90

113.55

-0.31


*Data excluded those parts of Jerusalem which were annexed by Israeli Occupation in 1967.