PCBS | Construction Cost Indices and Percent Changes by Major Groups in the West Bank*: January 2024 and February 2024

Construction Cost Indices and Percent Changes by Major Groups in the West Bank*: January 2024 and February 2024
(Base Year 2013=100)
Publish Date:24-03-2024
Click Here To Download Data as CSV File
Major GroupJanuary 2024 Residential buildingsFebruary 2024 Residential buildings% Change Residential buildingsJanuary 2024 Non- Residential buildingsFebruary 2024 Non- Residential buildings% Change Non-residential buildingsJanuary 2024 Skeleton BuildingsFebruary 2024 Skeleton Buildings% Change Skeleton Buildings
Raw materials110.72110.42-0.27109.88109.58-0.28109.05108.73-0.30
Hiring of equipment107.03107.240.20107.13107.460.31107.04107.270.21
Labour cost and wages 147.49147.490.00147.49147.490.00153.13153.130.00
General Index120.68120.50-0.15119.64119.46-0.16119.66119.45-0.18

Data exclude those parts of Jerusalem which were annexed by Israeli Occupation in 1967*