PCBS | Water Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: April 2024 and May 2024

Water Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: April 2024 and May 2024
(Base Month January 2010 =100)
Publish Date:25-06-2024
Click Here To Download Data as CSV File
Major and Sup GroupsApril 2024May 2024% Change
Water Reservoirs118.95120.771.53
Excavations131.85131.37-0.36
Concrete106.50106.47-0.03
Iron126.90132.744.61
Construction work and paint140.58140.580.00
Miscellaneous114.99114.990.00
Administrative expenses127.26127.260.00
Water Networks134.49134.36-0.10
Excavations131.85131.37-0.36
Deface Materials105.62105.20-0.40
Asphalt bitumen mixture and its products98.5498.540.00
Plastic and steel pipes 146.65146.60-0.04
Administrative expenses127.26127.260.00
Wages and other costs164.98164.980.00
General index129.63130.120.37

*Data exclude those parts of Jerusalem which were annexed by Israeli Occupation in 1967.