Construction Cost Indices and Percent Changes by Major Groups in the West Bank*: July 2024 and August 2024
(Base Year 2013=100)
Publish Date:29-09-2024
Click Here To Download Data as CSV File
Major Group | July 2024 Residential buildings | August 2024 Residential buildings | % Change Residential buildings | July 2024 Non- Residential buildings | August 2024 Non- Residential buildings | % Change Non-residential buildings | July 2024 Skeleton Buildings | August 2024 Skeleton Buildings | % Change Skeleton Buildings |
Raw materials | 112.24 | 112.53 | 0.26 | 111.33 | 111.62 | 0.26 | 111.83 | 112.27 | 0.39 |
Hiring of equipment | 106.43 | 106.63 | 0.19 | 106.44 | 106.64 | 0.18 | 106.43 | 106.63 | 0.19 |
Labour cost and wages | 148.39 | 148.39 | 0.00 | 148.39 | 148.39 | 0.00 | 154.11 | 154.11 | 0.00 |
General Index | 121.93 | 122.13 | 0.16 | 120.87 | 121.06 | 0.16 | 121.83 | 122.14 | 0.26 |