PCBS | Water Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: October 2024 and November 2024

Water Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: October 2024 and November 2024
(Base Month January 2010 =100)
Publish Date:23-12-2024
Click Here To Download Data as CSV File
Major and Sup GroupsOctober 2024November 2024% Change
Water Reservoirs122.62122.38-0.19
Excavations130.43130.38-0.04
Concrete105.53105.32-0.20
Iron138.46138.03-0.31
Construction work and paint146.00146.000.00
Miscellaneous116.65116.56-0.08
Administrative expenses127.49127.490.00
Water Networks135.86136.300.33
Excavations130.43130.38-0.04
Deface Materials108.11108.110.00
Asphalt bitumen mixture and its products99.0399.450.42
Plastic and steel pipes 148.96149.830.59
Administrative expenses127.49127.490.00
Wages and other costs165.07165.070.00
General index131.72131.950.18

*Data exclude those parts of Jerusalem which were annexed by Israeli Occupation in 1967.